U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Ellisville Site (RV007) - Removal Polrep
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region VII
|
Subject:
|
POLREP #15
Progress Report
Ellisville Site (RV007)
MOD980633010
Wildwood, MO
Latitude: 38.6001000 Longitude: -90.6041000
|
To:
|
|
From:
|
Heath Smith, OSC
|
Date:
|
8/8/2014
|
Reporting Period:
|
August 4 through August 8, 2014
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
0708 |
|
Contract Number: |
EP-S7-13-05 |
D.O. Number: |
0029 |
|
Action Memo Date: |
7/24/2014 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
NPL |
|
Operable Unit: |
00 |
Mobilization Date: |
3/24/2014 |
|
Start Date: |
3/24/2014 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
MOD980633010 |
|
RCRIS ID: |
MOD052623717 |
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
CERCLA incident category: Dioxin (D)
1.1.2 Site Description
1.1.2.1 Location
The Site is located in the extreme northeast corner of the proposed Strecker Forest Subdivision at 173 Strecker Road, Wildwood, Missouri, as well as a portion of the Bliss-Ellisville Site, west of the Mid-America Horse Arena at 149 Strecker Road, Ellisville, Missouri, and is approximately one acre in size. Coordinates for the Site are latitude 38.600100N, longitude 090.604100W. The Site has also been called the "northeast area" of the proposed Strecker Forest Subdivision in prior reports.
1.1.2.2 Description of Threat
See POLREP #1 (Initial POLREP).
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1 (Initial POLREP).
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
Due to the presence of elevated levels of dioxin in soil at the Site, the EPA is conducting a time-critical removal action to reduce potential exposure to nearby human populations, animals and the food chain. Removal criteria is set by the site's Action Memorandum. Soils exceeding 820 parts per trillion (ppt) from 0 to12 inches below ground surface (bgs) will be removed. At depths equal to or greater than 12 inches bgs, removal of soils will continue until a residual dioxin concentration of less than three times the site-specific cleanup goal, or 2,460 ppt, is reached.
Samples collected at this Site are being submitted to a laboratory in North Carolina for dioxin analysis. Turn-around between the time a sample is received by the laboratory and the time results are made available is 72 hours.
Dioxin-contaminated waste generated at this site is being treated as F027 dioxin-bearing waste. The Universal Treatment Standard (UTS) for F027 dioxin-bearing waste is 1 ppb (40 CFR § 268.48). The alternative Land Disposal Restrictions (LDR) treatment standard (40 CFR § 268.49) states that treatment to achieve constituent concentrations less than ten times the UTS is not required. Dioxin-contaminated waste generated during the removal, up to concentrations of 10 ppb 2,3,7,8-TCDD, will be transported to an off-site RCRA-permitted hazardous waste facility located in Waynoka, Oklahoma, for proper management.
Dioxin-contaminated materials with an average concentration greater than the alternative LDR treatment standard for contaminated soil will be managed by a facility capable of meeting the UTS for F027 dioxin-bearing waste.
Contaminated soil is being direct loaded into the red 25-cubic-yard roll-off boxes. Boxes are lined prior to filling and covered immediately after being loaded.
2.1.2 Response Actions to Date
August 4 through August 8, 2014
1) Crews finalized restoration activities within the work zone.
2) Two remaining boxes of waste will be shipped off next week.
3) Site office and remaining equipment will be demobilized next week as well.
Excavation area 3, Cell H/I |
Excavation complete. Restoration complete. |
Excavation area 3, Cell G |
Excavation complete. Restoration complete. |
Excavation area 3, Cell F |
Excavation complete. Restoration complete. |
Excavation area 3, Cell D/E |
Excavation complete. Restoration complete. |
Excavation area 3, Cell A/B/C |
Excavation complete. Restoration complete. |
Excavation area 2, Cell A/B |
Excavation complete. Restoration complete. |
Excavation area 1 |
Excavation complete. Restoration complete. |
Waste Box Inventory (as of August 8, 2014)
Boxes up to concentrations of 10 ppb 2,3,7,8-TCDD that have been transported to the off-site RCRA-permitted hazardous waste facility located in Waynoka, Oklahoma, for proper management: 84
Boxes awaiting shipment to Waynoka: 0
Boxes exceeding concentrations of 10 ppb 2,3,7,8-TCDD that have been transported to the off-site hazardous waste facility located in Saint-Ambroise, Quebec, for treatment and disposal: 15
Boxes awaiting shipment to Saint-Ambroise: 2
Boxes on site awaiting analytical profiling: 0
Boxes on site empty and waiting to be filled: 0
Air Monitoring - Results of air monitoring are being provided at http://www.epaosc.org/ellisville in the documents section. No additional air monitoring is planned.
Transportation and Disposal. To date 1,513 tons in 99 roll-off boxes have been shipped off site.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Enforcement options are being evaluated.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
Dioxin |
Soil |
1,276 tons |
multiple |
n/a |
Lone Mountain Landfill,
Waynoka, Oklahoma |
Dioxin |
Soil |
237 tons |
multiple |
thermal oxidation |
RSI high temperature treatment facility,
Saint-Ambroise, Quebec |
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
As of this operational period, contaminated soils from areas 1, 2 and 3 have been excavated. All areas have been backfilled and restored.
2.2.1.1 Planned Response Activities
Two waste boxes remain to be shipped off-site.
2.2.1.2 Next Steps
Crews and equipment will be demobilized.
2.2.2 Issues
No issues to report during this operational period.
|
|
2.3 Logistics Section
|
|
|
The existing road back to the work zone was improved with a 3-to-5 inch gabion stone overlaying a black geotextile fabric. The rock and fabric are used to allow the large equipment access to the back of the property. Due to the way the work zone is situated, including site drainage, it was determined that improving the existing road was the best option. In addition to on-site considerations, the impact on local residents was also considered. The path chosen allows for the least direct impact on local residential properties.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
2.5.1 Safety Officer
No safety issues were reported to the EPA by site staff.
2.5.2 Liaison Officer
A liaison officer was not required during this operational period.
2.5.3 Information Officer
The information officer for this project is:
Benjamin M. Washburn
Public Affairs Specialist
EPA Region 7
(913) 551-7364
|
3. Participating Entities
|
|
3.1 Unified Command
The limited span of control of this removal action does not warrant a full Incident Management Team (IMT) or Unified Command. Operations, safety, logistics, planning and finance functions will be handled by on-site project managers.
3.2 Cooperating Agencies
Coordinating agencies include: ATSDR, MDHSS, MDNR, USEPA Region 7, USEPA Headquarters and the City of Wildwood.
|
4. Personnel On Site
|
|
During this operational period the on-site crew was composed of the following:
EPA: One On-Scene Coordinator
START: One START Project Manager
ERRS: One Response Manager, One Operator and Two Laborers
|
5. Definition of Terms
|
|
ATSDR |
Agency for Toxic Substances and Disease Registry |
bgs |
below ground surface |
CERCLA |
Comprehensive Environmental Response, Compensation, and Liability Act |
EPA |
Environmental Protection Agency |
ERRS |
Emergency & Rapid Response Services Contract |
LDR |
Land Disposal Restrictions |
MDHSS |
Missouri Department of Health and Senior Services |
MDNR |
Missouri Department of Natural Resources |
mg/L |
milligrams per Liter |
mg/kg |
milligrams per kilogram |
NCP |
National Contingency Plan |
NRC |
National Response Center |
ng/m3 |
nanograms per cubic meter |
NPL |
National Priorities List |
OSC |
On-Scene Coordinator |
OSHA |
Occupational Safety and Health Administration |
OU |
Operable Unit |
PID |
Photo-Ionization Detector |
Polrep |
Pollution Report |
PPE |
Personal Protective Equipment |
PPM |
Part Per Million |
PPT |
Part Per Trillion |
PRP |
Potentially Responsible Party |
RCRA |
Resource Conservation and Recovery Act |
RPM |
Remedial Project Manager |
RSE |
Removal Site Evaluation |
Sitrep |
Situation Report |
START |
Superfund Technical Assessment and Response Team |
UTS |
Universal Treatment Standards |
VOC |
Volatile Organic Compound |
yd3 |
Cubic Yard |
|
6. Additional sources of information
|
|
6.1 Internet location of additional information/report
http://www.epaosc.org/ellisville
http://www.epa.gov/Region7/cleanup/strecker_forest/index.htm
6.2 Reporting Schedule
The Pollution Report (Polrep) serves as the OSC’s record of the response actions, notifications and decisions made to support the response action. Polreps will be completed and posted as conditions warrant and at the conclusion of site activities.
|
7. Situational Reference Materials
|
|
Please refer to the website http://www.epaosc.org/ellisville for all supporting documentation.
|
|
|